Dry Wall

This has been an exciting week for the project. The week started with painting the rafters black.

UNADJUSTEDNONRAW thumb 3239UNADJUSTEDNONRAW thumb 3238

The electrical and plumbing was completed and inspected so they could start hanging dry wall.

Here are the upstairs master bath, half bath, and closet areas.

UNADJUSTEDNONRAW thumb 3257UNADJUSTEDNONRAW thumb 324d

The door to the closet.(The former dark room door when the building was a photography studio in the 60’s as far as we know.)

UNADJUSTEDNONRAW thumb 3259

The downstairs bathrooms and janitors closet areas.

UNADJUSTEDNONRAW thumb 325c

And our garage area in the back of the building.

UNADJUSTEDNONRAW thumb 326e

And finally they poured the concrete next to the Otis Material Lift. 

UNADJUSTEDNONRAW thumb 3263

This upcoming week will be the remaining dry wall, electrical and plumbing finish outs, and the hanging of the lighting fixtures.

No Comments

Post a Comment