It’s been two weeks since the last update. I’ve been traveling for work but a lot has happened at the building.
Our shower is coming along. It will be Slate tile on the shower head wall and River Rock on the floor. Finally there will be a glass separator wall once they complete all the tile work.
The outside stairs are almost complete.
And we had our stainless steel countertop installed. It was interesting getting it upstairs. It did not look that big in the drawings:) It was custom ordered from Sealtex in Dallas. They were very professional and did an incredible job!!!!!
https://www.sealtex.com
Finally we started the railing around the Material Lift.
This week will consist of the installation of the sprinkler systems, electrical, flooring, and the finish of the HVAC. They have about half of the flooring complete. Its manufactured hardwood and looks incredible!!!!!!!