The 1st floor retail area restoration continues. Here is the East wall brick repair and repointing.
The bricks are three levels thick. Notice how some of the bricks in the middle level are collapsing.
An overview of the East wall restoration.
The West wall restoration.
And finally the floor restoration.
Here is where our contractor is tying the restored floors into the original flooring.
The brick work should be completed in the next few days. The flooring restoration will be at least another week. Afterwards we will seal the brick, stain/seal the floors, and finishing painting the walls and ceiling.