Downstairs Flooring – Projects

This weekend we finished cleaning up under the downstairs floorboards. Our contractor is going to start in 2 weeks on replacing the bad floor joists. Afterwards they will install a new sub-floor and re-install the original floor boards. Finally, we will have them sanded and sealed for another 50 years of usage:)

UNADJUSTEDNONRAW thumb 350c

UNADJUSTEDNONRAW thumb 3508

Here are the original floorboards to be re-installed. We still need to remove nails and place them in piles based on size to make it easier for the flooring contractor.

UNADJUSTEDNONRAW thumb 3509

We had to make room in our garage area to place all the extra wood from the retail area. We are storing any extra wood for future projects.

UNADJUSTEDNONRAW thumb 3507

As for the upstairs, we continue to work on numerous projects. Here is the buffet we just finished painting. We still need to mount a painting above it.

UNADJUSTEDNONRAW thumb 350d

An overview picture of the buffet placement between the front door and kitchen area.

UNADJUSTEDNONRAW thumb 350b

In the next couple of weeks we will be finishing the downstairs, having the upstairs front door replaced, and cleaning up the bar stools to be placed along the kitchen island. The front door was not installed correctly and we are having to replace it.

More Projects

We continue to gain more and more projects. Here is an antique buffet we are restoring to go upstairs next to our front door. We are going to place our white marble Italian statues on it.

UNADJUSTEDNONRAW thumb 34f4

Another project is bar stools. We had the pads recovered and now we need to clean the metal, paint where needed, and then put them back together. We are going to place them along the Kitchen Island and the Camera Bar.

UNADJUSTEDNONRAW thumb 34f0

We also were able to clean out one of our storage units. Only one more to go!!!!!

UNADJUSTEDNONRAW thumb 34f3

This is a part from the Consolidated Lithograph we are turning into a bar area upstairs that we had in storage.

UNADJUSTEDNONRAW thumb 34f2

Finally this past week we had our internet speeds increased. When we moved in we went with AT&T. All AT&T could provide us was DSL at 18Mbps down and 2 Mbps up. Everything was slow and our security cameras would not work correctly. We finally changed over to Spectrum Business, Its 400 Mbps down and 20 Mbps up. Much better.They did have some challenges though getting it into the building and avoiding the power lines.

UNADJUSTEDNONRAW thumb 34f1

Banister Renovation

Nothing really new to report. We are still restoring the original banisters to reuse on the stairs to the 2nd floor loft area. The past couple of weeks have been working with the bank and contractors to work out the final details on the remaining items. This week is a Holiday week so we do not expect much progress other than coordination.I’m hoping to gather some good video footage over the July 4th Holiday and will post them as I take them.

Until then, enjoy the beautiful warm weather here in Cleburne Texas!!!!!

 

UNADJUSTEDNONRAW thumb 2ee2

UNADJUSTEDNONRAW thumb 2ee3

Reclamation & Revival

This week we focused on reclaiming some original parts of the building and some architectual salvage we found here and there. Our contractor continues to plumb the upstairs and they began the electrical work.

Upstairs plumbing rough-in courtesy of Mr. Bill’s Plumbing (Thanks Robert!).

UNADJUSTEDNONRAW thumb 2ea4

UNADJUSTEDNONRAW thumb 2ea6

The electricians are starting to bring in supplies.

UNADJUSTEDNONRAW thumb 2eaa

Look, new electric boxes!

UNADJUSTEDNONRAW thumb 2ea9

To comply with fire codes we had to reverse the direction of the interior stairs.  We asked the builder to keep the banisters. Our plan is to strip them and refinish them so they can be reused. The one shown below is one solid piece of wood that is 18’ (feet, yes feet) long. 

UNADJUSTEDNONRAW thumb 2eab

Ok, I may have over estimated my abilities, HGTV makes it look so easy!  The banisters had been stained, then painted beige, blue, and finally green. Have i mentioned how much i like Ready Strip. It’s the only way I could do this.  It’s a little ‘gooey’ but it works.  Like we said, the plan is to stain them and reinstall them on the new interior staircase.  And look at the results, the banisters haven’t even been sanded or refinished in this picture and they are incredibly beautiful.   

 

UNADJUSTEDNONRAW thumb 2eb0

Finally, we wanted to share some Architectural Salvage we have found to add to the decor.

This is going to be our master bathroom vanity (salvaged and repurposed) with our vessel sinks and the new faucets (Amazon) that just arrived.

UNADJUSTEDNONRAW thumb 2eb6 

And a set of accordion doors we have modified to be used upstairs on the Material Lift. They still need to be stripped and repainted.

UNADJUSTEDNONRAW thumb 2ead

 

Renovation Update

We are getting close. All of the plans are at the City and we should be receiving final permits and approvals real soon. Until then, we are cleaning and prepping as much as we can prior to the contractor starting interior work.

Pictures of upstairs.UNADJUSTEDNONRAW thumb 2dd1UNADJUSTEDNONRAW thumb 2dd2UNADJUSTEDNONRAW thumb 2dd3UNADJUSTEDNONRAW thumb 2dd0Here we are priming the former dark room door that was upstairs. We are going to paint it to match the walls and install it as a 2nd doorway into the closet.

UNADJUSTEDNONRAW thumb 2dcf

Cleaning and painting lights that will be located over the kitchen island.

UNADJUSTEDNONRAW thumb 2dccUNADJUSTEDNONRAW thumb 2ddb

And finally some other lighting that we are still working into the design.

UNADJUSTEDNONRAW thumb 2ddaUNADJUSTEDNONRAW thumb 2dd9

Lastly some projects we will need to get started on soon. Our future wine rack and coffee bar.

UNADJUSTEDNONRAW thumb 2dd6UNADJUSTEDNONRAW thumb 2dd7