Final Push

It’s the final week before Candlewalk. The only things left are cosmetic and cleaning.

The shower is finished with a wall of glass.

UNADJUSTEDNONRAW thumb 3370

We continue to clean and paint the Otis Material Lift.

UNADJUSTEDNONRAW thumb 336d

UNADJUSTEDNONRAW thumb 336e

The brick is almost finished being sealed.

UNADJUSTEDNONRAW thumb 3362

The stairs still needed finishing.

UNADJUSTEDNONRAW thumb 336a

Downstairs we are cleaning and preparing for decorations.

UNADJUSTEDNONRAW thumb 336b

UNADJUSTEDNONRAW thumb 3363

Also downstairs they finished the riser for the Fire suppression System. We have done everything we can until the City extends the water main across the street.

UNADJUSTEDNONRAW thumb 336f

And finally the sign in front of the building for the Candlewalk Tour Home. This week we will be painting, cleaning, and staging upstairs.

UNADJUSTEDNONRAW thumb 3369

Getting Closer

We are getting closer. They finished painting the front and west sides of the building.UNADJUSTEDNONRAW thumb 3219UNADJUSTEDNONRAW thumb 3229

They started framing of the 2nd floor windows. When we installed the new windows they temporary installed them to dry in the building. Now they are finishing the installation.

UNADJUSTEDNONRAW thumb 3221

HVAC continues downstairs.

UNADJUSTEDNONRAW thumb 3223UNADJUSTEDNONRAW thumb 3217

And we started to seal the upstairs brick in the shower area.

BeforeUNADJUSTEDNONRAW thumb 320e

AfterUNADJUSTEDNONRAW thumb 3220UNADJUSTEDNONRAW thumb 3222

Finally framing is almost complete. Here is the rotating door to the closet. We salvaged it from the building when there was a photography business upstairs and they had a dark room door.

UNADJUSTEDNONRAW thumb 3228

Exterior Painting

We are starting to get noticed!!!!! Almost everything up to this point has been inside and not exposed to the general public. This week, all of that has changed. We were going to wait until the very end to paint the exterior walls but they needed it completed prior to installing the fire escape stairs on the west wall. The weather slowed them down but they should finish everything this upcoming week. 

UNADJUSTEDNONRAW thumb 31fbUNADJUSTEDNONRAW thumb 31ef

The exterior painting is being completed by Guillermo’s Painting located at 2209 N. Main St. Ste 168, Cleburne, TX