Windows & Cabinets

We have windows and cabinets!!!!!! This past week they finished installing the windows on the West side of the building.

UNADJUSTEDNONRAW thumb 2fb7UNADJUSTEDNONRAW thumb 2fc5And then we had our cabinets installed. The island is a whopping 5′ x 12’!!!!!!

UNADJUSTEDNONRAW thumb 2fbaUNADJUSTEDNONRAW thumb 2fc1

Saturday we met with Seal Tex to measure the countertop. We are having installed a custom Stainless Steel Countertop with build in sink.

https://www.sealtex.com/residential

And finally they continued to work on the HVAC. Its getting close!!!!

UNADJUSTEDNONRAW thumb 2fcaUNADJUSTEDNONRAW thumb 2fc9UNADJUSTEDNONRAW thumb 2fd0

Side Window Video

Uncategorized

Here is a short video of the side windows. I was playing around with my drone and make a quick video. I’m planning over the holiday weekend to spend some time and get smoother videos of the building that are not so jerky.

This is just a teaser:)

Window Cutouts

We are getting closer. They finished opening up the windows upstairs and have started on the two cutouts downstairs.

UNADJUSTEDNONRAW thumb 2f80This will be our view looking out the front door toward the Johnson County Courthouse Tower.

UNADJUSTEDNONRAW thumb 2f8c

Our kitchen cabinets will be located between these windows.

UNADJUSTEDNONRAW thumb 2f81

They are continuing to install the HVAC and plumbing upstairs.UNADJUSTEDNONRAW thumb 2f7cUNADJUSTEDNONRAW thumb 2f7d

And downstairs the electrical continues.

UNADJUSTEDNONRAW thumb 2f8b

Here is the door opening between the bathroom downstairs.UNADJUSTEDNONRAW thumb 2f8d

And finally some pictures of the outside.UNADJUSTEDNONRAW thumb 2f88UNADJUSTEDNONRAW thumb 2f89

This upcoming week they will be finishing the 1st floor door cutouts, measuring for the exit stairs, and continuing on the electrical buildout.

Upstairs Windows

This has been a busy week for the building. They have started to install the 4 x 5 Ton HVAC units, 2 upstairs and 2 downstairs.

UNADJUSTEDNONRAW thumb 2f54UNADJUSTEDNONRAW thumb 2f5b

The plumbing continues….

UNADJUSTEDNONRAW thumb 2f5f

But the best news so far is they have started to cut out the windows upstairs!!!!

UNADJUSTEDNONRAW thumb 2f51UNADJUSTEDNONRAW thumb 2f57UNADJUSTEDNONRAW thumb 2f5cUNADJUSTEDNONRAW thumb 2f55UNADJUSTEDNONRAW thumb 2f37

And finally where our front door and emergency exit will be located.

UNADJUSTEDNONRAW thumb 2f58

The best one is when the sun was setting and they had just started. That is the Johnson County Clock Tower.

UNADJUSTEDNONRAW thumb 2f32

New Windows

During the asbestos removal they had to remove the old windows and window seals. The City gave us approval to install the new windows until the final Engineer Drawings are reviewed and approved. Here are the new windows.